Task
Name |
Start
Date |
End
Date |
Phase
1 - Preliminary Watershed Assessment |
August 7
2002 |
December 31
2002 |
Existi8ng
Data Compilation |
August 7
2002 |
December 4
2002 |
Existing
Water Quality Data Evaluation |
September 26 2002 |
December 4
2002 |
Identification of Data
Gaps/Trenches/Needs |
September 26
2002 |
December 4
2002 |
Existing
Land Use and Evaluation |
August 7
2002 |
December 4
2002 |
Public
Outreach/Surveys |
August 7
2002 |
December 4
2002 |
Build-Out
Analysis |
August 7
2002 |
December 4
2002 |
Impervious Cover
Survey |
August 7
2002 |
December 4
2002 |
Presentation
Of Preliminary Findings to Technical Team |
December 4
2002 |
December 4
2002 |
Project
Organization/Structure/Responsibilities |
August 7
2002 |
December 4
2002 |
Public
Kick-Off Meeting with Technical Team |
December 4
2002 |
December 4
2002 |
Goal Setting
Based on Public Input |
December 4
2002 |
December 4
2002 |
Phase 11–
Watershed Assessment |
January 1
2003 |
June 30
2004 |
Streamwalk
Evaluation of Waterways |
January 1
2003 |
September 1
2003 |
GIS
Mapping/Database Design |
August 7
2002 |
December 4
2002 |
Stream Flow
Studies and Groundwater Withdrawal Evaluations |
July 1
2003 |
June 30
2004 |
Stormwater
Management Evaluation |
September 26
2002 |
June 30
2005 |
Level 1
Rosgen Study |
July1
2003 |
June 30
2004 |
Stream
Modeling (Forest Hill Run) |
September 26
2002 |
June 30
2003 |
Lake Impact
Evaluation (Lake Crawford) |
July 1
2003 |
June 30
2004 |
Water
Quality Monitoring |
September 26
2002 |
June 30
2004 |
Mid-Phase 11
Technical Team Meeting |
October 1
2003 |
October 1
2003 |
End Phase 11
Technical Team Meeting |
June 30
2004 |
June 30
2004 |
Public
Meeting With Technical Team |
June 30
2004 |
June 30
2004 |
Phase 3-
Watershed Restoration and protection Plan Development |
July 1
2004 |
June 30
2005 |
Detailed
report of watershed assessment finding |
July 1
2004 |
June 30
2005 |
Detailed
description of restoration needs |
July 1
2004 |
June 30
2005 |
Restoration
recommendations/Options |
July 1
2004 |
June 30
2005 |
Detailed
description of protection needs |
July 1
2004 |
June 30
2005 |
protection
recommendations/Options |
July 1
2004 |
June 30
2005 |
Search of
funding options for recommended actions |
July 1
2004 |
June 30
2005 |
Presentation
of final plan to public and stakeholders |
June 30
2005 |
December 31 2005 |
Funded by a
Growing Greener Grant from the PA Department of
Environmental Protection
To
Contact Us Use The Information Below
Debra
Brady
R.R.
#1, Box 1226 · Cresco, Pa
18326
Phone: 570-595-8840
· Fax:
570-595-3090
Email:
debbrady@paradisecreekwatershed.org
Home |
About
The
Paradise Creek Watershed |
About The
Project |
Data And Information |
Project
Timeline |
Study Results |
Links
"This site was originally designed
and created by the Pocono Mountain West High School Environmental Club
in 2003"
Website Maintained, Hosted by
PoconoGIS